Program Status Page
Program Year 2012 Status
AEP-TCC 2012 - Updated 1/25/2012
| Budget
Status |
Res. |
Non-Res. |
Total |
| A. Current Budget |
$180,000 |
$180,000 |
$360,000 |
| B. Requested (In Queue) |
$9,275 |
$100,800 |
$110,075 |
| C. Reserved |
$131,301 |
$132,462 |
$263,763 |
| D. Paid |
$17,280 |
$0 |
$17,280 |
|
# of completed projects |
1 |
|
1 |
| kW-dc installed |
8.640 |
0.000 |
8.640 |
|
Avg. $/watt incentive |
$2.00 |
#DIV/0! |
$2.00 |
| E. Available to Reserve
(A-C-D) |
$31,419 |
$47,538 |
$78,957 |
|
|
|
|
| Budget Status |
Res. |
Non-Res. |
Total |
| Req+Res+Paid as % of Budget |
88% |
130% |
109% |
| Res+Paid as % of Budget |
83% |
74% |
78% |
| Paid as % of Budget |
10% |
0% |
5% |
|
|
|
|
| Application Process Status |
Res. |
Non-Res. |
|
| Accepting Applications |
Yes |
Yes |
|
| Approving Applications |
Yes |
Yes |
|
| Incentive Level for New Approvals |
$1.75 |
$1.50 |
|
AEP-TNC 2012 - Updated 1/25/2012
| Budget
Status |
Res. |
Non-Res. |
Total |
| Original Budget |
$90,000 |
$90,000 |
$180,000 |
| 2011 Rollover |
|
$0 |
$0 |
| Amendment 1 |
|
-$19,000 |
-$19,000 |
| A. Current Budget |
$90,000 |
$71,000 |
$161,000 |
| B. Requested (In Queue) |
$43,848 |
$0 |
$43,848 |
| C. Reserved |
$64,890 |
$25,200 |
$90,090 |
| D. Paid |
$25,110 |
|
$25,110 |
|
# of completed projects |
2 |
|
2 |
| kW-dc installed |
11.160 |
0.000 |
11.160 |
|
Avg. $/watt incentive |
$2.25 |
#DIV/0! |
$2.25 |
| E. Available to Reserve
(A-C-D) |
$0 |
$45,800 |
$45,800 |
|
|
|
|
| Budget Status |
Res. |
Non-Res. |
Total |
| Req+Res+Paid as % of Budget |
149% |
35% |
99% |
| Res+Paid as % of Budget |
100% |
35% |
72% |
| Paid as % of Budget |
28% |
0% |
16% |
|
|
|
|
| Application Process Status |
Res. |
Non-Res. |
|
| Accepting Applications |
Yes |
Yes |
|
| Approving Applications |
Yes |
Yes |
|
| Incentive Level for New Approvals |
$1.75 |
$1.50 |
|
SWEPCO 2012 - Updated 1/25/2012
| Budget
Status |
Total (Res Only) |
| A. Current Budget |
$121,500 |
| B. Requested (In Queue) |
$0 |
| C. Reserved |
$0 |
| D. Paid |
$0 |
|
# of completed projects |
0 |
| kW-dc installed |
0.000 |
|
Avg. $/watt incentive |
na |
| E. Available to Reserve
(A-C-D) |
$121,500 |
|
|
| Budget Status |
Res. |
| Req+Res+Paid as % of Budget |
0% |
| Res+Paid as % of Budget |
0% |
| Paid as % of Budget |
0% |
|
|
| Application Process Status |
Res. |
| Accepting Applications |
Yes |
| Approving Applications |
Yes |
| Incentive Level for New Approvals |
$1.75 |
Program
Year 2011 Results
AEP-TCC 2011 (updated 1/25/2012 - not final)
| | Res. | Non-Res. | Total |
|
A. Final Budget |
$180,375 |
$410,000 |
$590,375 |
|
D. Paid |
$162,420 |
$360,000 |
$522,420 |
|
# of completed projects |
10 |
4 |
14 |
|
kW-dc installed |
88.965 |
456.920 |
545.885 |
|
Avg. $/watt incentive |
$1.83 |
$0.79 |
$0.96 |
| Incentive levels offered ($/w-dc) | $2.00 | $1.75 | |
AEP-TNC 2011 (updated 1/25/2012 - not final)
| | Res. | Non-Res. | Total |
|
A. Final Budget |
$96,049 |
$84,679 |
$180,728 |
|
D. Paid |
$69,656 |
$41,279 |
$110,935 |
|
# of completed projects |
6 |
2 |
8 |
|
kW-dc installed |
32.778 |
21.600 |
54.378 |
|
Avg. $/watt incentive |
$2.13 |
$1.91 |
$2.04 |
| Incentive levels offered ($/w-dc) | $2.25 | $2.00 | |
SWEPCO 2011 - (updated 1/25/2012 - not final)
| Budget Status |
Res. |
Non-Res. |
Total |
|
A. Final Budget |
$137,414 |
$185,806 |
$322,219 |
|
D. Paid |
$47,960 |
$185,806 |
$233,766 |
|
# of completed projects |
4 |
8 |
12 |
|
kW-dc installed |
22.315 |
96.746 |
119.061 |
|
Avg. $/watt incentive |
$2.15 |
$1.92 |
$1.96 |
Program Year
2010 Results
|
|
AEP-TCC |
|
|
| Program
Year 2010 |
Res. |
Non-Res. |
Total |
|
A. Final Budget |
$201,500 |
$325,550 |
$527,050 |
|
D. Paid |
$201,125 |
$95,550 |
$296,675 |
|
# of completed projects |
13 |
2 |
15 |
|
kW-dc Installed |
83.042 |
38.430 |
121.472 |
|
Avg. $/watt incentive |
$2.42 |
$2.49 |
$2.44 |
| Incentive levels offered ($/w-dc) | $2.50 | $2.50 | |
|
|
AEP-TNC |
|
|
| Program
Year 2010 |
Res. |
Non-Res. |
Total |
|
A. Final Budget |
$167,040 |
$180,000 |
$347,040 |
|
D. Paid |
$166,313 |
$180,000 |
$346,313 |
|
# of completed projects |
12 |
5 |
17 |
|
kW-dc Installed |
67.085 |
117.775 |
184.860 |
|
Avg. $/watt incentive |
$2.48 |
$1.53 |
$1.87 |
| Incentive levels offered ($/w-dc) | $2.50 | $2.50 | |
|
|
SWEPCO |
| Program
Year 2010 |
Total |
|
A. Final Budget |
$287,400 |
|
D. Paid |
$207,475 |
|
# of completed projects |
9 |
|
kW-dc Installed |
132.690 |
|
Avg. $/watt incentive |
$1.56 |
| Incentive level offered ($/w-dc) | $2.50 |
Program Year
2009 Results
|
|
AEP-TCC |
|
|
| Program
Year 2009 |
Res. |
Non-Res. |
Total |
|
A. Final Budget |
$84,450 |
$275,550 |
$360,000 |
|
D. Paid |
$12,950 |
$180,000 |
$192,950 |
|
# of completed projects |
1 |
2 |
3 |
|
kW-dc Installed |
5.180
|
105.300
|
110.480
|
|
Avg. $/watt incentive |
$2.50
|
$1.71
|
$1.75
|
|
|
AEP-TNC |
|
|
| Program
Year 2009 |
Res. |
Non-Res. |
Total |
|
A. Final Budget |
$90,000 |
$90,000 |
$180,000 |
|
D. Paid |
$12,960 |
$0 |
$12,960 |
|
# of completed projects |
1 |
0 |
1 |
|
kW-dc Installed |
5.180
|
0.000
|
5.180
|
|
Avg. $/watt incentive |
$2.50
|
na |
$2.50
|
| Incentive level offered ($/w-dc) | $2.50 | $2.50 | |
|
|
SWEPCO |
| Program
Year 2009 |
Total |
|
A. Final Budget |
$90,000 |
|
D. Paid |
$27,600 |
|
# of completed projects |
2 |
|
kW-dc Installed |
11.040
|
|
Avg. $/watt incentive |
$2.50
|
| Incentive level offered ($/w-dc) | $2.50 |